It will be as wide as my room and go to the corner of the house so it will be about 12 x 12 ft.
Roof is framed in and we are able to stay dry!
Now you can see my door and window placement.
Walls going up. Now it is starting to look like something. :)
Rick my contractor. The insulation and floor are going in. We had strong winds and hail almost everyday for this part of the work! Geesh! I put sawdust down to get us out of the mud.
Floor joists up.
The footings are done, ready for the beam.
This is the beginning, we started the last week in March. Rick my contractor was great! He was very flexible and patient and let me do as much stuff as I was able to save money on the project. In this picture the forms for the footings are being made. I dug the holes, lots of mud and the weather didn't cooperate much!



.jpg)

.jpg)
1 comment:
What a fantastic space you'll have! Congratulations on the progress.
Post a Comment